PDWP reduces underpasses and revises cost for Rawalpindi Mall Road project

The Provincial Development Working Party (PDWP) approved a revised project cost for the Rawalpindi Mall Road signal-free corridor. The number of planned underpasses for the corridor decreased from three to two.
Specifically, the proposed underpass at Army Graveyard Chowk was dropped from the scheme. This removal resulted in an overall project cost reduction of Rs1.0842 billion.
Conversely, the cost for the Race Course Underpass increased by more than Rs1.36 billion, moving from Rs3.09 billion to Rs4.459 billion. Furthermore, the Charing Cross Underpass saw a cost escalation exceeding Rs901.6 million, rising from Rs2.58 billion to Rs3.49 billion.
The revised project is now scheduled for completion by the end of November.